Free tool

Sprint Capacity Calculator

Work out how many hours your team really has this sprint — and how many story points to commit to based on your past velocity.

Frequently asked questions

How do you calculate sprint capacity?+

For each person: (working days in the sprint − days off) × hours a day × the share of their time on this team × a focus factor. Add everyone up for the team's capacity in hours.

What is a focus factor?+

The share of the day left for sprint work after meetings, support, reviews and interruptions. Many teams use 60–80%. Start with 70% and adjust it to match what your team actually delivers.

How many story points should we commit to?+

Take your average velocity from the last few sprints and scale it by this sprint's capacity compared with a normal sprint. If two people are off for half the sprint, commit to fewer points. The range uses your lowest and highest recent sprints.

Is velocity a target?+

No — it's a forecasting tool for the team. Pushing velocity up as a goal tends to inflate estimates rather than speed up delivery.

Can velocity be tracked automatically?+

Yes. TeamTrackin's scrum boards record what each sprint finished and show burndown and velocity reports, with planning poker and stand-ups on the same board.